SO FAR –

The initial stage

Initial sketch was prepared and fundraising began

Community consultation

Cost for initial stage – £1,700

The development stage is complete

The project group commissioned a design by a Landscape Architect. The plan has now been finalised and ‘frozen’ ready for the building stage.

Fundraising paid for:

  • Modification of the concept design in line with the community consultation report
  • Preparation of detailed design drawings
  • Preparation of the outline specification and establishment of the cost to build the pathway

Battle Town Council allocated funds for:

  • Topographical survey

Cost for developmental stage – £4,200 inc. VAT (excluding topographical survey)

NEXT – the building stage …

  • More fundraising for the community contribution towards the building costs (10% of the cost) so we are aiming for £22,000
  • Secure capital funding
  • Appoint contractors
  • BUILD!

Estimated cost to build – £220,000